An EOT crane load test verifies the bridge, trolley and hoist of an overhead travelling crane. After no-load checks, the crane is tested at rated load, then at a proof load โ commonly 125% of SWL per international practice โ while brakes, limit switches and deflection are checked. A certified test report records the results.
Load testing electric overhead travelling cranes in UAE factories and warehouses. The regulatory context behind Dubai crane testing is covered in our work equipment inspection regulations guide.
What the Test Covers and When It Is Required
An Electric Overhead Travelling crane is the workhorse of UAE factories, workshops and warehouses: it runs on elevated rails along the building, with a bridge spanning the bay, end carriages carrying the bridge along the runway, and a trolley travelling along the bridge carrying the hoist. Every component moves, and every component is loaded during a lift โ so the load test addresses each element: the hoist is proven for its rated and proof load, the trolley is travelled under load, and the bridge is run along the runway with the load positioned to stress it while deflection is measured.
Three triggers bring a facility to testing. The first is commissioning: a newly installed EOT crane is load tested before it starts production duty, giving the baseline certificate factories keep on file. The second is periodic thorough examination, where the crane's regime includes proof load testing at defined intervals. The third is repair or modification โ a new hoist, re-roping, re-geared machinery or structural repair ends the old test evidence.
In the UAE, factories and warehouse operations are routinely asked for current test certificates by clients, insurers, or authority and municipality-linked inspections, and a lapsed test can stop production on the spot. Keeping the load test current is an operational matter, not paperwork. Confirm the applicable interval and load with the inspection body.
The Test Sequence: No-Load, Load and Proof
Testing proceeds from light to heavy, in a fixed order. The no-load stage exercises the crane empty: hoisting and lowering, trolley travel, bridge travel, limit switches and controls, confirming everything behaves before weight is applied. The load stage then lifts the rated load and runs the crane through its working motions with that load, checking brakes and smooth travel under working conditions. Below-the-hook accessories follow the quarterly colour rotation โ charted in our lifting colour code chart 2026.
Only then is the proof load applied โ commonly 125% of SWL per international practice โ held for its defined period and observed while deflection is measured. Skipping ahead to the proof load wastes the value of the earlier stages, because faults found empty are cheaper to fix than faults found under overload. The sequence is summarised below.
| Stage | Load Applied | Purpose and Key Checks |
|---|---|---|
| No-load test | Empty hook | Hoist, trolley and bridge travel; limit switches; controls |
| Load test | 100% rated load | Brake holding on hoist and travel; operation under working load |
| Proof test | Commonly 125% of SWL | Structural adequacy of hoist, trolley and bridge; deflection within limits |
Brakes, Limit Switches and Deflection
Brakes are the safety element most tested under load. The hoist brake must hold the load when the crane is stopped; trolley and bridge brakes must hold the crane on its travels. During the test, the load is stopped deliberately at each motion to demonstrate holding โ a brake that lets a load creep is a fail, and a slipping brake on an EOT crane in a factory bay is a serious finding.
Limit switches are proven with the load on the hook: the hoist upper limit trips before the hook assembly reaches a dangerous position, and travel limits function on the trolley and bridge. Deflection of the bridge under the proof load is measured and compared with the permissible deflection limit set by the applicable standard and the crane's design. Confirm the specific deflection limits for your crane's span and class with the inspection body.
Common Findings and What They Mean
Most EOT load test findings cluster in three places. Brake creep โ a hoist load that drifts slowly downward with the brake applied โ points to worn friction linings or misadjustment, and the crane stays out of service until it is corrected and re-tested. Limit switch maladjustment, where the upper limit trips late or not at all, is a straightforward correction that prevents a hook over-travel into the structure.
Deflection beyond the permissible limit is the finding that matters most structurally: it suggests the bridge is overloaded for its class, fatigued, or was designed to a different duty than the certificate claims. After any finding, the correction is documented and the relevant part of the test repeated, so the final report records a crane that passes, not one that passed before the fault. Per international practice, the inspection body decides what must be repeated after rectification.
Preparing the Factory for the Test
The area under the crane bay is controlled like any lift zone. Production is cleared from beneath the load path, the floor below is barricaded, and personnel are briefed that test loads will be suspended overhead. Test loads need planning: certified weights are the simplest for smaller cranes, while larger capacities may use water bags filled on site to the required mass, so nothing heavy needs to be hauled through the plant.
The crane's documents are assembled first โ capacity plate, prior reports, maintenance records โ so the inspector can verify the rated duty before any load is applied. Access to the crane gantry, working lighting and clean walkways all affect how smoothly the test runs, whether the facility sits in Dubai's industrial areas, Mussafah in Abu Dhabi, or a Sharjah free zone. Agree the schedule and the production downtime window with the inspection body in advance so plant planning is not surprised.
The Load Test Report
The report closes the process. A complete EOT load test report identifies the crane and its rated capacity, states the loads applied at each stage, records hold periods, brake and limit switch results, and deflection measurements, and closes with a pass or fail conclusion carrying the competent person's signature and the date.
Factories should file the report with the certificate and review both before the next thorough examination. The history of deflection and brake results across successive tests is what reveals whether a crane is ageing gracefully or drifting toward a problem. QIC (Quality International Certifications), a UAE inspection company since 1998 that performs load testing, issues EOT crane test reports and certificates for factories and warehouses.
Checklist
- Assemble crane documents, capacity plate and prior test reports.
- Verify the rated SWL before planning the proof load.
- Clear and barricade the area under the load path.
- Brief plant personnel that test loads will be suspended.
- Run no-load checks: hoist, trolley, bridge, limits, controls.
- Test with rated load: brakes and travel under working load.
- Apply the proof load, commonly 125% of SWL, and hold.
- Measure bridge deflection and compare with the permissible limit.
- Prove all limit switches with load on the hook.
- Inspect for permanent deformation after unloading.
- File the signed report and certificate together.
EOT-specific requirements sit inside the general test framework โ the crane load test UAE overview covers mobile, tower and EOT crane classes together.
Frequently Asked Questions
What is an EOT crane load test?
A structured test of an overhead travelling crane in which the hoist, trolley and bridge are proven under controlled loads. It runs from no-load checks through rated load to a proof load, commonly 125% of SWL, verifying structure, brakes, limit switches and deflection, and finishing with a certified report.
What proof load is applied to an EOT crane hoist?
Per international practice the proof load for an EOT crane hoist is commonly 125% of its safe working load, applied statically and held while the structure is observed and deflection is measured. The exact percentage for your crane and configuration should be confirmed with the inspection body before testing.
How often should overhead cranes be load tested in UAE?
Load tests are required at commissioning and after major repair or modification, and periodically under the crane's thorough examination regime. Intervals depend on the crane's duty, usage and the requirements of clients or authorities. Confirm the applicable periodicity for your facility with the inspection body.
Who can conduct an EOT crane load test?
A competent person from a recognised inspection body, working with the facility's crane operator and maintenance team. The test report and certificate must carry the competent person's signature. Third-party inspection companies in the UAE routinely perform EOT crane load testing for factories and warehouses.
What is checked during EOT crane load testing?
Hoisting and lowering under load, brake holding on the hoist, trolley and bridge, travel of the trolley and bridge with load, operation of limit switches, and bridge deflection under the proof load against permissible limits. The crane is also inspected after unloading for permanent deformation or defects.